February, 2007 Update:
Partition is being completed as per schedule
Sheet rock installation is being completed.
Electrical installation is progressing as per schedule.
Metal and wood framing are being completed as per schedule.
The retaining wall has been completed. Water proofing, foundation drains and backfilling of the wall are being done.
Br. Ardahji’s installers are installing the data/TV cables to all rooms. Materials are paid by IEFK and the labor is donated.
A professional PA system, sound system is being negotiated with a contactor to be installed in the cafeteria and the Masjid area upstairs.
The final contract to dig a sewage line is being negotiated for the best bid.
The materials for the drop-down ceiling are being provided by the Odom Construction for selection before installation. The ceiling will be installed after the interior painting is complete by IEFK task force (volunteers).
Earthworks provided an estimate for grading work and await final evaluation and approval by IEFK engineers.
Asphalt paving wait for contractors’ bids such as Best Paving and Duracap.
Interior floor coverings are being selected.
January 2007 Update:
November 2006 Update:
If you have questions or need more information please contact any of the members on the construction management team.